Healthcare Construction: Understanding ICRA Classification and Infection Control Requirements

Healthcare construction is one of the most demanding sectors of the construction industry. Unlike conventional commercial construction, renovation and maintenance activities in hospitals, medical offices, and outpatient facilities must be performed while protecting patients, healthcare personnel, and ongoing clinical operations.

Even relatively minor construction activities, such as opening a ceiling, installing electrical conduit, or removing drywall, can introduce airborne contaminants into sensitive healthcare environments.

This is where Infection Control Risk Assessment (ICRA) becomes an essential part of construction planning.

What Is ICRA?

Infection Control Risk Assessment (ICRA) is a systematic process used to identify and mitigate infection-related risks associated with construction, renovation, maintenance, and demolition activities within healthcare facilities.

The American Society for Health Care Engineering (ASHE) developed the ICRA 2.0 framework to help construction professionals, facility managers, and infection prevention teams evaluate these risks and establish appropriate protective measures.

The assessment considers several factors:

  • Type and complexity of construction activities.

  • Patient population and vulnerability.

  • Location and function of the affected healthcare department.

  • Adjacent occupied spaces, including floors above and below.

  • Potential for airborne dust and contaminants.

  • Existing HVAC systems and airflow conditions.

  • Ability to isolate the construction area.

Understanding Construction Activity Types

Construction activities are generally divided into four categories:

Type A — Inspection and Noninvasive Activities

Visual inspections, limited maintenance, and activities that do not generate significant dust or disturb building systems.

Type B — Small-Scale, Short-Duration Activities

Minor repairs, limited ceiling access, and small electrical or mechanical installations with controlled dust generation.

Type C — Moderate Construction and Renovation

Activities involving removal of fixed building components, drywall cutting, flooring removal, and other work generating moderate to significant dust.

Type D — Major Construction and Demolition

Extensive demolition, major renovation, structural modifications, and substantial mechanical or electrical system replacement.

Understanding Patient Risk Groups

The sensitivity of the healthcare environment is equally important when determining infection control requirements.

ICRA identifies four patient risk groups:

  • Low Risk

  • Medium Risk

  • High Risk

  • Highest Risk

Administrative offices, patient treatment areas, operating rooms, intensive care units, and oncology departments may require substantially different levels of protection.

The risk assessment must also consider surrounding departments, shared ventilation systems, and potential pathways for airborne contaminants.

The Five ICRA Classes

The combination of construction activity and patient risk determines the preliminary class of infection control precautions.

ICRA Class

General Level of Protection

Class I

Basic infection prevention and dust avoidance

Class II

Limited dust-control precautions for eligible activities

Class III

Enhanced dust control, isolation, and environmental protection

Class IV

Critical containment, controlled airflow, and pressure monitoring

Class V

Highest level of containment and infection control precautions, including additional entry and personnel controls

Specific requirements must be determined using the applicable ASHE ICRA 2.0 guidance and healthcare facility policies.

Essential Infection Control Measures in Healthcare Construction

Depending on the required ICRA classification, construction teams may need to implement:

  • Temporary or rigid construction barriers.

  • Fire-rated containment assemblies where required.

  • HEPA-filtered negative air machines.

  • Continuous differential pressure monitoring.

  • HVAC supply and return isolation.

  • Sealed penetrations and controlled access points.

  • Anterooms and personnel entry procedures.

  • Adhesive walk-off mats.

  • Daily cleaning and containment inspections.

  • Controlled construction debris transportation.

  • Final cleaning and inspection before containment removal.

These measures should be incorporated into the construction schedule, subcontractor scope of work, and project budget during preconstruction.

Why ICRA Matters During Preconstruction

Infection control requirements directly affect construction costs, productivity, sequencing, and project duration.

Failing to identify these requirements early can result in additional costs, schedule delays, operational disruptions, and unacceptable risks to patients and healthcare personnel.

A properly planned infection control strategy allows construction teams to establish realistic budgets, coordinate subcontractors, minimize disruptions, and maintain a safer healthcare environment throughout construction.

Free ICRA Classification Calculator

To simplify preliminary infection control planning, Kubus Construction is sharing a free online ICRA Field Guide designed for construction professionals, project managers, engineers, estimators, and superintendents.

The tool allows users to:

  • Select the healthcare environment and patient risk category.

  • Identify the type of construction activity.

  • Evaluate adjacent spaces.

  • Determine a preliminary ICRA classification.

  • Review applicable infection control precautions.

  • Calculate preliminary containment and negative air equipment requirements.

  • Generate downloadable PDF assessment reports.

The calculator is mobile-friendly and designed for use during preconstruction meetings, site walks, and field assessments.

Launch the Free ICRA Calculator

Building Safer Healthcare Environments

Successful healthcare construction requires more than technical construction expertise. It requires careful planning, coordination with clinical operations, and a comprehensive understanding of infection prevention requirements.

Integrating infection control into every stage of construction helps protect patients, maintain healthcare operations, and support successful project delivery.

Disclaimer: The ICRA Field Guide is an independent educational and preliminary planning tool. It is not an official ASHE product and does not replace a facility-approved ICRA assessment, infection control permit, or professional judgment. All classifications and protective measures must be verified and approved by the applicable healthcare facility and Infection Prevention team before construction begins.

Reference: American Society for Health Care Engineering — ASHE ICRA 2.0 Toolkit.